Please be advised that alternating lane closures will take place on the Tobin Bridge lower level starting Tuesday, May 2, 2007 through Thursday May 31, 2007 for the installation of cable and outriggers.
Lower level, 2 lanes closed alternating right to left, Midnight to 5:00 a.m.
Lower level, 1 lane closed, alternating right to left from 5:00 a.m. to 2:00 p.m.
All work is traffic and weather permitting.
This work is in preparation for the continuation of painting on the Tobin Bridge. Painting will occur on the upper and lower levels of the Little Mystic Truss to the toll plaza area as well as along the upper level CANA approach spans in Charlestown. Once the sites are prepared, work will take place through November 2007, at which time the project will end for the winter and begin again in the spring of 2008.